Storing cement through the monsoon

Cement is meant to be used within 3 months of the week printed on the bag, and IS 269:2015, as the Ministry of Railways set it out in a February 2022 CAMTECH pamphlet, requires bagged cement standing longer than that in a vendor's hands to be retested before use.

  • Guides
  • 1 table of figures
  • Own delivery, 34 blocks
  • Open all 7 days

Jay Shree Infra sells cement across the counter in Saharsa and out into Supaul and Madhepura, and this rack is where a monsoon bag comes off it. Not every size is in every brand on a given day. What holds whatever name is on the sack is below: how long the clock runs, where it starts, and what a stack has to stand on while it runs. The makers do not fully agree with each other about any of it.

Damp is the whole of the problem and it does its work quietly. UltraTech writes on its own site that cement reacts quickly with moisture in the air, that even slight dampness can start the setting process inside a closed bag, and that once cement has lumped it does not get its quality back. So a bag is rarely ruined by rain falling on it. It goes through the air of a shut room, up through a floor, in through a small tear, over weeks in which the stack looks exactly as it did the day it was built. So the net bag weight, the manufacturing date and the batch are numbers to read off the actual pack in front of you, never assumed from a brand or a size.

The numbers

What three published sources put on a cement stack

Bags in a stack, height off the floor, and the age at which a bag becomes a question, as each source publishes it.

Scroll the table sideways to see every column

Published byBags in a stackat mostOff the floorat leastAge at which it is a questionmonths from packing
UltraTech10 / 15150 mm3
Nuvoco10nothing publishednothing published
IS 269:2015nothing publishednothing published3

UltraTech is one row and two figures, because it publishes both. Its article on storing bags at a site says not more than 10 bags high; its article on keeping cement in condition says not more than fifteen. On the floor height the same two pages agree: at least 150 mm on the first, six to eight inches on the second, which is the same plank. Nuvoco's own monsoon note says ten. The IS 269:2015 row is the requirement as the Ministry of Railways set it out in February 2022, and it is the only row here that is a standard rather than a maker writing about its own product.

Build to the smaller number. Two of the three sources say ten, and the reason both UltraTech and Nuvoco give for the limit is the same one: bags low in a tall stack are under pressure, and pressure makes lumps. Fifteen is not wrong, it is simply the looser of two figures one company prints about its own cement.

The floor line is the one that earns its keep once the rain sets in. UltraTech's reason for it is groundwater: a floor holds moisture and that moisture works up into the bottom bags, in a stack that is dry everywhere a hand can reach. A wooden plank or a pallet under the bottom course is the cheapest fix in a monsoon stack, and it is the one most often skipped.

What the bag has to carry

The week on the sack, and the best before that follows from it

A bag of ordinary portland cement carries eight markings, and two of them are dates. One is the batch or control unit number, given in terms of the week, the month and the year of packing. The three that carry no figure at all are the maker's name and its trademark, the name and designation of the cement itself, and the address of the manufacturer. The other is a best before date, which the requirement fixes at 3 months from the date of packing. A third line spells out in words that cement more than 3 months old needs testing to check conformity before it is used. All three are printed on the sack together, so a bag too old to use without a test says so on its own paper.

The same list carries an instruction that is not a date and belongs here anyway: the words Use No Hooks. UltraTech gives the reason on its storage page. A hook tears the bag, a tear lets air and moisture in, and a hole small enough to miss is enough to harden cement inside a sack that still looks whole from the outside.

Net quantity is on the list too, at 50 kg per bag unless something else is specified. Do not lean on that number: it moves across SKUs and regions, so the weight printed on the sack in front of you is the weight, and the 50 kg is only the default that printing is measured against.

The clock

Where the three months are actually spent

The IS 269:2015 wording is exact about whose hands the cement is in. Cement held in bulk at the factory before shipment gets six months. Cement in bags, in local storage such as in the hands of a vendor, gets 3 months after the completion of tests, and then a retest before use. A dealer is that vendor, so the clock runs on a bag sitting in a dealer's godown just as it runs on one already at your site.

Which means the three months do not start on the day you buy. They start at the week printed on the sack, and part of them has already gone by the time a load is standing in a village in Supaul.

That is why the order of a stack matters more than how neat it looks. Both makers say the same two things about it: take the oldest bags first, and take out of the stack only what the day's work needs. UltraTech adds the check that costs nothing, which is to refuse bags that are already hard or lumpy at the time of delivery. The moment to look is while the vehicle is still standing there.

At this counter

How a wet season load gets put together here

Tell us the day the work starts and tell us where the bags will stand until then, because a covered room and a sheet in an open yard are two different loads. We reach all 34 blocks of Saharsa, Supaul and Madhepura in our own vehicles, tempo to tractor to truck, charged at the market rate for that route. Ask us to read the packing week off the bags before they go on the vehicle, and ask it again if the order is split across two trips.

Cement rarely travels alone. Binding wire, cover blocks and waterproofing liquid ride out with the bori, and the sheet that covers the sacks covers those too. What each sack actually is, bag by bag, sits on its own page: UltraTech and Nuvoco are the two makers quoted above, and the sariya weight chart does the same job for the steel going on the same trip.

The retest

What a retest checks, and where the pamphlet's word ends

A retest is a laboratory job, not a look. No opinion given at a counter can settle whether one particular bag is still fit for work; the standard's own answer to a sack past its date is a test for conformity, done in a lab.

The CAMTECH pamphlet is guidance from the Ministry of Railways on IS 269:2015, and it says on its own first page that it does not replace the standard's existing provisions. Where an engineer, a department or a tender names a rule stricter than what is set out here, that stricter rule is the one for your job.

Questions

Barsat me cement rakhne ke sawal

Barsat me cement kitne din tak rakh sakte hain?

Three months from the week printed on the bag, and that figure is the standard's and not ours. IS 269:2015, as the Ministry of Railways set it out in February 2022, treats bagged cement in a vendor's hands as due for a retest once it has stood more than 3 months after the completion of tests. UltraTech publishes the same 3 months as its ideal and says a properly stored bag may reach 6 months with its strength falling over that time. Buy to the work in front of you and the question does not come up.

Bori par hafte aur saal ki chhap kahan hoti hai?

In the marking block, as the batch or control unit number, which is given in terms of the week, the month and the year of packing. The same block carries a best before date fixed at 3 months from packing, and a line saying that cement older than 3 months needs testing to check conformity. Ring +91 6202 967 218 and we will read those figures off the stack before the vehicle loads.

Ek ke upar kitni boriyan rakhi ja sakti hain?

Ten is the figure to build a monsoon stack to. UltraTech's storage article says not more than 10 bags high and Nuvoco's monsoon note says ten as well, while UltraTech's other page allows fifteen. Both companies give one reason for the limit, which is that bags low in a tall stack sit under pressure and pressure makes lumps.

Zameen par seedhe bori rakhne me kya dikkat hai?

The floor holds water and the bottom bags take it. UltraTech asks for wooden pallets or a raised platform at least 150 mm above the ground, and puts that height at six to eight inches on its other page. Nuvoco says the same thing in words, planks or pallets and never the bare ground, and gives ground moisture as the reason.

Gaanth padi bori chalegi ya phenk dein?

Do not settle it by hand and do not settle it on a website. UltraTech's instruction is to refuse bags that are already hard or lumpy at the time of delivery, and it writes that cement which has taken moisture and lumped does not get its quality back. Past 3 months the standard's answer is a test for conformity before use, which is laboratory work. Call +91 6202 967 218 with what you are looking at and we will tell you what can be checked on the ground.

Before you order

Five answers that decide a monsoon load

Each one settles something the figures above cannot.

  • Which packing week is on the bags standing today?

    It is the start of the clock and it is printed on every sack. We will read the week, the month and the year off the stack before anything is loaded.

  • Where will the bags stand until the work starts?

    A shut room, a shed or an open yard under a sheet are three different answers, and they decide whether the plank under the bottom course is worth arranging before the vehicle comes.

  • How many bori does the work in front of you actually need?

    The clock is already running on every bag in the stack, so a month of spare cement bought in July is a month of the best before date spent in a yard.

  • Does the vehicle need to go out covered?

    Say it when the load is booked and not when the driver leaves. It changes what goes on the vehicle with the bori, since the same sheet has to cover the wire and the blocks.

  • Can somebody look at the sacks while the vehicle is still there?

    UltraTech's own instruction is to refuse bags that are hard or lumpy at delivery. That check takes a minute on the ground and cannot be done later.

Contact

The week on the bag decides this

The one figure nobody can tell you over the phone is how old the sack in front of you is, and that figure is printed on the sack itself. Read us the week, the month and the year off the marking block and we will say where that bag sits against its own best before date. Ring +91 6202 967 218 with the count and the day the work starts, and the stack that leaves here leaves oldest first.